From the same architect and structural engineer behind the Burj Khalifa, Jeddah Tower takes the buttressed-core system to its logical extreme — stripping outrigger trusses and perimeter mega-columns entirely, sinking 270 piles up to 105 m into Red Sea reef limestone, and solving the 1 km elevator problem with KONE's carbon-fiber UltraRope. After a seven-year construction freeze triggered by Saudi Arabia's 2018 anti-corruption purge, the project hit 100 floors and 400 m on 26 April 2026, and is on pace for August 2028 completion as the first structure in history to exceed one kilometer.



| Date | Milestone |
|---|---|
| April 2013 | Ground broken, 270-pile boring program begins |
| December 2013 | All piles complete |
| September 2014 | Above-grade structural concrete begins |
| January 2018 | Work halted at floor 63 — SBG chairman detained |
| September 2023 | JEC issues new tenders to 14+ contractors |
| January 2025 | Construction resumes; SBG re-contracted for SR 7.2 B |
| March 2025 | Turner Construction takes over project management |
| April 2025 | Floor 66 |
| October 2025 | KONE elevator contract signed (67 units) |
| January 2026 | Floor 80 |
| March 2026 | Floor 93 |
| April 2026 | Floor 100 / 400 m |
| August 2028 | Projected completion |

| Metric | Burj Khalifa (2010) | Jeddah Tower (target 2028) |
|---|---|---|
| Height | 828 m (549 m occupied) | ≥ 1,008 m (638 m highest occupied floor) |
| Structural system | Buttressed core + outrigger trusses + perimeter mega-columns | Pure buttressed core — no outriggers, no mega-columns |
| Architect | Adrian Smith (SOM) | Adrian Smith (AS+GG) |
| Structural engineer | Thornton Tomasetti | Thornton Tomasetti |
| Wind engineering | RWDI, 27-orientation test program | RWDI, continuous-taper aerodynamic form |
| Foundation piles | 192 × 1.5 m dia., ~43 m deep | 270 × 1.5–1.8 m dia., 45–105 m deep |
| Raft thickness | ~3.7 m | 4.5–5.0 m |
| Elevator hoist rope | Conventional steel wire | KONE UltraRope carbon-fiber (4 observatory shafts) |
| Top elevator speed | ~10 m/s (Burj destination) | 10 m/s (double-deck to highest occupied floor in 52 s) |
| Tuned mass dampers | None | 870 t (floor 206) + 260 t (floor 218) — spire only |
| Total concrete | ~330,000 m³ (est.) | ~500,000 m³ |
| Construction cost (tower) | ~$1.5 billion | ~$1.2 billion (SR 7.2 B contract to SBG) |
en.wikipedia.org
gulfconstructiononline.com
constructiondigital.com
thorntontomasetti.com
skyscraper.org
global.ctbuh.org