www.enr.com

The Grand Ethiopian Renaissance Dam stores the Blue Nile's single wet season and hands it out across the year; this issue covers how 10.4 million m³ of roller-compacted concrete was placed, what the flood, drought and sediment cases forced, and why the release rules remain unsettled.
| What it is | The figure | What the figure forced |
|---|---|---|
| Purpose | Power for a country where fewer than a third of people had grid electricity in 2011, and exports to neighbours | A dam that stores the wet season and releases it across the year, which is where the dispute now sits 4 |
| Type and size | Roller-compacted concrete gravity dam, 145 m from the riverbed to the crest at 655 m above sea level, 1,780 m long | A gravity dam holds the water back with its own weight, so it needs sound rock rather than the arch's rock abutments; the designer gives the maximum structural height as 175 m, which counts the powerhouse section below river level 25 |
| Concrete | About 10.4 million m³ of roller-compacted concrete, by the utility's figures; the contractor's project page states 10.7 million | Placing that volume set the project schedule, and the annual placement record for the type 26 |
| Saddle dam | 4.9 km long, 50 m high, concrete-faced rockfill with about 16.5 million m³ of fill, roughly 3.5 km from the Sudan border | Closes the low ground beside the main dam and carries the emergency spillway 2 |
| Reservoir | 74 billion m³ total, 59.2 billion live and 14.8 billion dead; 1,874 km² at the full supply level of 640 m; 246 km long | Holds about a year and a half of the Blue Nile's average flow, 48.5 billion m³ a year at the El Diem gauge near the border 3 |
| Catchment | 172,250 km² of the Ethiopian highlands | The flow arrives in one wet season and carries the sediment of one of the most eroded basins in the world 23 |
| Flood case | Three spillways together sized for a probable maximum flood of 30,200 m³/s, routed at 18,000 m³/s; the gated spillway passes 14,700 m³/s through six gates | The gated spillway takes ordinary floods, the ungated one at full supply level takes the ten-year event, and the emergency spillway takes the thousand-year event 25 |
| Drought case | Two bottom outlets at 542 m, about 42 m above the riverbed | Water can be sent on to Sudan and Egypt while the reservoir sits below the level the turbines need 2 |
| Turbines | 13 Francis units, eleven at 400 MW and two at 375 MW, working on a head of 83 to 133 m | Installed capacity follows the dry-season flow, so the plant holds more generators than the river can keep busy 24 |
| Annual output | About 15,700 GWh in a typical hydrological year | Roughly a third of what 5,150 MW would produce running flat out 7 |
| Cost | A $4.8 billion contract in 2011, about $5 billion at completion; 91 percent financed at home through bonds and payroll contributions, with about $1 billion from China's Exim Bank for turbines and electrical works | The financing protected the schedule from lenders' conditions and tied it to the country's own cash flow 27 |
| Timeline | Foundation stone 2 April 2011; first power 20 February 2022; inaugurated 9 September 2025 | Fourteen years, against an early expectation that the first two turbines would run by 2015 2 |
| Operating rules | No binding agreement among Ethiopia, Sudan and Egypt on filling or operation | Releases are set by the operator alone, and the downstream states treat that as the risk 18 |





thenationalnews.com
en.wikipedia.org
pietrangeli.com
webuildgroup.com
commons.wikimedia.org
commons.wikimedia.org
commons.wikimedia.org
This story was produced automatically by a channel. One sentence is all it takes for Neodrop to keep producing for you.